Whiskey Creek Transmission Main and PS

Owner

District of Nanaimo

Project Completion

May 2023

Project Description

As Prime Contractor for the project, Tritech was responsible for the supply and installation of the Service Area Transmission Main and Pump Station for the District of Nanaimo.

Overcoming Challenges/ Value Added

Long lead time on specified pumps, provided alternate pumps with a shorter lead time which met project requirements and provided additional space inside the small pump station footprint.

Developed bypass pumping plan and installed system to bypass pump station during mechanical and electrical work with minimal shut down period. Kept alarms and monitoring systems running during construction period.


Supply & Installation of a new 75mm Transmission main that connected the well site to the potable water reservoir and pump station. The pump station at the reservoir site was upgraded to include:
  • New distribution pumps, piping and instrumentation which included process and electrical work
  • Installation of a new generator
  • HVAC
  • Temporary Pump Station Bypass
  • Surface restoration
  • Construction Survey layout, Traffic control, Vehicle access