Squamish Wastewater Treatment Plant Upgrades

Owner

District of Squamish

Project Completion

April 01, 2025

Project Description

The District of Squamish is undertaking an extensive upgrade of the Mamquam Wastewater Treatment Plant. The WWTP upgrades consist of construction of a new circular bioreactor/clarifier tank, associated piping and a new septage receiving station. Ground under the proposed circular tank has been excavated to approx.1.5m below grade. Impacted utilities under the proposed circular footprint have been decommissioned and relocated.

Challenges/Constraints

The work must be done in a manner that allows the treatment plant to continue operating and meeting the discharge permit throughout the duration of the work.

WWTP

  • Excavation and rough grading for new bioreactor clarifier.
  • Placement and compaction of granular materials and geotextiles
  • Concrete tank construction, including in tank piping and miscellaneous metal platforms, handrails, etc.
  • Supply and installation of process equipment.
  • Installation of clarifier mechanism and associated accessories pre-purchased by owner.
  • Construction of Flow splitter chamber for secondary treatment.
  • Modifications to rectangular clarifier to convert into Primary Clarifier.
  • Primary sludge conveyance pipe to DAFT.
  • Inlet piping from Grit tanks to proposed Primary Clarifier.
  • Conveyance piping from Primary Clarifier to Flow split chamber.
  • Conveyance piping from Flow split to two bioreactors.
  • Associated plant piping and tie-ins to existing piping, structures and equipment.
  • Power and control wiring and electrical kiosks.
  • Civil finish grading around designated work areas.

Septage Receiving Station

  • Rough excavation and site preparation
  • Placement and compaction of granular materials.
  • Underground buried piping and tie-ins.
  • Power and control conduits and wiring from new SRS building to existing Control Building.
  • Construction of new SRS building and all mechanical/electrical building equipment/components.
  • Installation of District supplied Septage Receiving Equipment.
  • Construction of new access road for septage trucks.
  • Fence modifications

Most Recent Entries

Scroll to Top