The District of Squamish is undertaking an extensive upgrade of the Mamquam Wastewater Treatment Plant. The WWTP upgrades consist of construction of a new circular bioreactor/clarifier tank, associated piping and a new septage receiving station. Ground under the proposed circular tank has been excavated to approx.1.5m below grade. Impacted utilities under the proposed circular footprint have been decommissioned and relocated.
Challenges/Constraints
The work must be done in a manner that allows the treatment plant to continue operating and meeting the discharge permit throughout the duration of the work.
WWTP
- Excavation and rough grading for new bioreactor clarifier.
- Placement and compaction of granular materials and geotextiles
- Concrete tank construction, including in tank piping and miscellaneous metal platforms, handrails, etc.
- Supply and installation of process equipment.
- Installation of clarifier mechanism and associated accessories pre-purchased by owner.
- Construction of Flow splitter chamber for secondary treatment.
- Modifications to rectangular clarifier to convert into Primary Clarifier.
- Primary sludge conveyance pipe to DAFT.
- Inlet piping from Grit tanks to proposed Primary Clarifier.
- Conveyance piping from Primary Clarifier to Flow split chamber.
- Conveyance piping from Flow split to two bioreactors.
- Associated plant piping and tie-ins to existing piping, structures and equipment.
- Power and control wiring and electrical kiosks.
- Civil finish grading around designated work areas.
Septage Receiving Station
- Rough excavation and site preparation
- Placement and compaction of granular materials.
- Underground buried piping and tie-ins.
- Power and control conduits and wiring from new SRS building to existing Control Building.
- Construction of new SRS building and all mechanical/electrical building equipment/components.
- Installation of District supplied Septage Receiving Equipment.
- Construction of new access road for septage trucks.
- Fence modifications